The new Lansing bridge over the Mississippi opened Friday, months ahead of schedule
The Good Day La Crosse team
If you've been riding the ferry at Lansing, you can drive across again. The new WIS 82/Iowa 9 bridge opened Friday after a ribbon-cutting with Gov. Tony Evers. It was originally set to open in spring 2027. Iowa DOT director Scott Marler shouted "We did it!" from the middle of the span.
The $165 million bridge by the numbers
- $165 million
- for the project that began in late 2023
- 160,000+
- vehicles carried by the free ferry during its year of service
- 6,600 tons
- of steel in the new bridge
- 11,400
- cubic yards of concrete in the new bridge
Source: WKOW
The old Black Hawk Bridge stood for 94 years and closed for good in late 2025. The new lanes are 12 feet wide, with room for bike lanes, and WXOW says the river channel is 100 feet wider for barges. Iowa DOT project manager Clayton Burke credited a crew that worked seven days a week, 10 hours a day.
- Ferry's last ride: 9:15 p.m. Friday, from Iowa to Wisconsin
- Expected traffic: about 2,500 vehicles a day
- Winter work: ferry landings restored, old piers removed
- Spring 2027: deck work brings disruptions, not full closures
The bridge opened about five months before its spring target
- Late 2023Construction on the $165 million project began.
- Nov. 2025WisDOT and Iowa DOT started free temporary car ferry service.
- Nov. 6The new bridge opened to traffic after a ribbon-cutting.
- Spring '27Original target for opening the new bridge.
- 2027The entire Lansing Bridge project is expected to be complete in late spring.